Environmentally friendly renovation with cork
Set an example in terms of sustainability with underlay made from renewable raw materials. Our SELITeco® 2 mm cork is made from natural cork and is not only environmentally friendly but also high-performance. Thanks to its compressive strength, it efficiently protects the floor from loads and, thanks to its low thermal resistance, it is suitable for combination with underfloor heating systems.
Before installation, please note: Check the base in accordance with CEN/TS 14472 and ensure that the quality of the base is suitable for proper processing. In general, the base should be clean, level, dry, resistant to tension and compression and should not contain any substances such as plasticisers, solvents or other diffusing substances. It must be ensured that the base is in a state of equilibrium humidity and that the CM value is below 2.0 % (for cement screed) or below 0.5 % (for anhydrite screed and anhydrite flowing screed). The processing instructions of the flooring manufacturer are to be observed as binding specifications.
Cleaning the surface
Cleaning the surface
Step 1 Clean the surface thoroughly with a brush or vacuum cleaner. Remove any adhesive and paint residues completely.
Applying the moisture protection
Applying the moisture protection
Step 2 Mineral bases need protection against rising moisture. Cover the room completely with SELITstop® Comfort Vapour Barrier. Allow the joints to overlap by approx. 5 cm and seal them in a vapour-tight manner with SELITstop® Aluminium-Foil Sealing Tape.
Masking the wall connection area
Masking the wall connection area
Step 3 In the wall connection area, place the film in a trough-like position at approx. 3-4 cm to protect against moisture and fix to the wall with SELITstop® Aluminium-Foil Sealing Tape. Alternatively, use SELITstop® Moulding Protection Belt. In this case, install the moisture protection film flush with the wall.
Laying out the first panel
Laying out the first panel
Step 4 Lay the first panel of the underlay over the entire width of the room.
Installing the flooring
Installing the flooring
Step 5 Lay the flooring in the same orientation as the underlay. Do not place any weight on the underlay, if necessary place the panel under your knees/feet to distribute the load.
Finishing the installation
Finishing the installation
Step 6 Repeat steps 4 to 5 until the flooring has been installed throughout the entire room.
Technicaldata(according to EN 16354)
Punctual conformability (PC)
up to 0.5 mm
Compressive strength (CS)
≥ 90 kPa
Compressive creep (CC)
≥ 25 kPa
Dynamic load (DL25)
≥ 100,000 Zyklen
Resistance to large ball (RLB)
≥ 50 cm
Water vapour diffusion resistance (SD)
–
Thermal resistance (R)
∼ 0.042 m²K/W
Impact sound reduction (IS)
up to 17 dB
Reaction to fire (RTF)
Ffl
*Suitability for underfloor heating
Yes, if flooring R ≤ 0,108 m²K/W (e.g. laminate up to approx. 8 mm)